Shutdown Management 
You can use this business process to manage a shutdown (or outage) of a plant or a facility. The process involves scheduling all of the work in a critical time window, and completing the required work on time and within the budget assigned to the shutdown. The key to the success of the process is to have a close relationship between the actual work being performed and the overall schedule and budget.
This process assumes that work orders have already been planned and any required links or relationships between the work orders have been established. A planned order should already have all the required instructions and parts required to complete the order.

The following business process runs in SAP ECC:
...
1. Create shutdown revision
2. Assign orders to revision
3. Create project
4. Update project with activities and relationships
5. Assign orders to activities
6. Add additional link to details on orders
7. Maintain project budget
8. Perform project cost planning
9. Perform project scheduling
10. Schedule orders from project planning
11. Review activity operation float
12. Perform material availability check from order
13. Perform capacity evaluations
14. Perform capacity leveling
15. Review project information (activity overview, Gantt chart, budget)
16. Release project
17. Release orders
18. Establish baseline
19. Manage work
20. Adjust schedule
21. Review floats, versions, capacities
22. Complete work
23. Perform analysis
Properly executed, a large project will run on time and within the planned budget.