Show TOC

Process documentationDetermining Short/Over Differences

 

In this process the short/over differences are calculated according to one of three methods indicated in the Short/Over Balancing Customizing:

  1. Copy expected amount and short/over amount from Totals Records POS transactions.

  2. Copy expected amount from Totals Records POS transactions and calculate short/over amount

  3. Calculate expected amount and short/over amount from related sales and financial POS transactions

The short/over and the expected amounts are calculated as follows:

Calculation

Description

Short/Over Amount = Actual Amount - Expected Amount

Actual Amount refers to the amount of tenders physically counted at the register.

Expected Amount = Tender Amount + Pay-In Amount - Pay-Out Amount

Pay-In Amount refers to the amount added to the till.

Pay-Out Amount refers to the amount removed from the till.

For methods 1 and 2 listed above, Pay-Out Amount = Removal Amount + Bank Amount, where Removal Amount refers to the amount removed from the till and Bank Amount refers to the amount transferred to the bank.

For method 3, Tender Amount is calculated from the POS transactions associated to the Totals transaction. Pay-In and Pay-Out amounts are calculated from the Financial transactions associated to the Totals transaction.

Prerequisites

You have made the following settings in Customizing:

  • You have set the type of the task to be carried out under Start of the navigation path Tasks Next navigation step One-Step Processing Next navigation step Define Tasks End of the navigation path depending on the requirements for either Immediate Processing or Collective Processing and you have checked the correctness of the other task settings.

  • Under Start of the navigation path POS Transactions End of the navigation path, you have verified that an appropriate task group is assigned to the relevant transaction types.

  • You have ensured that the task group, which is assigned to the transaction type of your POS transaction, exists under Start of the navigation path Tasks Next navigation step Define Task Group End of the navigation path .

  • You have ensured that the task to be carried out is assigned to the relevant task group under Start of the navigation path Tasks Next navigation step Assign Tasks to Task Group End of the navigation path.

  • You have activated and customized the short/over parameters under Short/Over Balancing.

Process

The task 0060 Calculation for Short/Over Balancing is available in the standard system for determining the short/over differences.

You carry out processing of the task for the relevant POS transactions depending on the task type. For more information, see Task Processing.

If the task has been carried out successfully, the system sets the task status for all processed POS transactions to Completed.

You can carry out task processing with the PIPE Dispatcher (transaction /POSDW/PDIS). For more information, see Using the PIPE Dispatcher.