Displaying Report Overview / Controlling The
End-of-Day Processing Chain
The function Overview of reports in end-of-day processing and control of an end-of-day processing chain enables you to find the status of the started end-of-day process runs. These reports provide you with more details to enable you to control runs, for example, to restart them.
You can only restart a job chain if you have activated the Restart Possible indicator in Customizing under Periodic Tasks ® Include Customer Reports in Mass Processing.
...
1. Choose Periodic Tasks ® End-of-Day Processing ® Overview.
2. If you require an overview of a different period, change the predefined current date as necessary.
3. Start the program.
The system displays a list of the runs started for end-of-day processing in the selected period with the following information:
Run date, additional identification characteristic of the chain on the run date, user who started the run, and the status.
9 At least one step terminated, restart not possible
E Completed
W Active or restart possible
You need to maintain this list, whereby if you want to delete entries, select them and choose Edit ® Delete. If you confirm the query, the selected entries are deleted.
4. Select a run and choose Detail Display.
The system displays a detailed list of the reports from this end-of-day processing run. If you can restart the end-of-day processing chain, the system displays restart and restart individual step.
You can determine further processing of the chain by using this list:
Display job overview
Restart end-of-day processing chain
Restart end-of-day processing chain terminated with errors in individual step
5. To continue processing the chain, choose Restart. If you want to continue end-of-day processing for a certain report, select this report in the list and choose Restart Individual Step.