Long-term and Short-term Lot
Sizing Procedure 
You can apply lot size indicators at material-level and SKU-level, like Scheduling and Number of Periods to long-term/short term lot-sizing. You can also deactivate maximum lot-size and minimum lot-size in the long-term.
You must do the following:
● Define the valid from date of the long-term lot size area in the group box End of the short-term period/start of the long-term period via the following indicators:
○ Period Ind: Long-term Lot Size
○ Number of periods
● Calculate the beginning of the long-term period by taking todays' date and adding the number of periods in the future. The long-term planning period then starts on the next complete period.

You must define a maximum MRP period for materials that are planned using the short and long-term lot size in the Define Maximum MRP Period screen. This will help to include the materials in planning after a certain period even if no changes relevant to the planning run have occurred. This avoids a situation where order proposals created with the long-term lot size move into the short-term period because no changes relevant to MRP have occurred for that material.
A material that is planned on a regular basis must also be provided with an MRP type that contains the indicator for regular MRP.
You must also do the following in Customizing:
● To make the short-term/long-term lot-sizing procedures work for AFS, you must maintain entries for controlling the lot-sizing in AFS Customizing by choosing Production ® Material Requirements Planning ® Planning ® Lot-Size Calculation ® Check Lot-Sizing Procedure.
Choose MRP Lot Size and ensure that following indicators are specified for short and long-term period:
○ Lot-sizing Procedure
○ Lot-size Indicator
○ Numberof Periods
○ Scheduling (Optional)
○ Check Minimum Lot Size (Optional)
○ Check Maximum Lot Size (Optional)
● To make the short-term/long-term lot-sizing procedures work for AFS, you must maintain separate entries for short and long-term lot sizing in AFS Customizing by choosing Production ® Material Requirements Planning ® Planning ® Lot-Size Calculation ® Define Lot-Sizing Procedure for AFS.
For this you must maintain the following columns:
○ MRP lot-sizing key (Column LS)
○ Lot-sizing procedure (Column LS)
○ Lot-sizing indicator (Column LI)
○ Function module name

By activating the Customizing for short-term/long-term lot-sizing procedure, AFS MRP selects one lot-sizing procedure in the near future and a different one in the distant future. You can use the lot-sizing procedure to determine how the system is to calculate the reorder quantity during MRP.