Use
The maintenance of the lot-sizing procedures in AFS is based on the procedure you already know from the SAP standard as well as on procedures developed especially for AFS. You can use periodic and statistical lot-sizing procedures in AFS. Combined with other functions of the AFS MRP, lot-sizing procedures can have different effects (see
Lot Sizes in MRP).Features
In AFS the lot sizes are calculated using default quantities from the respective material master record or by combining requirement quantities of one or several periods to one lot size. This is valid for both the SAP lot-sizing procedures you use in AFS as well as for the lot-sizing procedures that are especially developed for AFS. You can maintain lot sizes both at material level and at SKU level. Note that this can lead to inconsistencies.
The following lot-sizing procedures are supported by AFS.
|
Lot Size ID |
Description |
|
EX |
Exact lot-size calculation |
|
FX |
Fixed lot-size calculation |
|
X1 |
Requirements distribution ratio - monthly |
|
X2 |
Requirements distribution ratio - weekly |
|
X3 |
Requirements distribution ratio - daily |
|
X4 |
SKU group procedure 1 - monthly |
|
X5 |
SKU group procedure 1 - weekly |
|
X6 |
SKU group procedure 1 - daily |
|
XA |
SKU group procedure 2 - monthly |
|
XB |
SKU group procedure 2 - weekly |
|
XC |
SKU group procedure 2 - daily |
|
MB |
Monthly lot size |
|
PK |
Period lot size by planning calendar |
|
TB |
Daily lot size |
|
WB |
Weekly lot size |

The procedures X1 to XC are the procedures that are especially developed for AFS (see
Requirements Distribution Ratio, SKU Group Procedure 1, and SKU Group Procedure 2).AFS Restrictions
AFS does not support any dynamic lot-sizing procedures.