Start of Content Area

Function documentation ATP against Planning Locate the document in its SAP Library structure

Use

With this standard function you can carry out the availability check for planned independent requirements in sales orders instead of for existing inbound and outbound elements. That way planned independent requirements can be consumed with confirmed quantities for the sales order during the goods receipt.

Prerequisites

To use ATP against planning, you must maintain the following in Customizing:

There must also be independent requirements.

Features

The consumption of planned independent requirements is based on the AFS consumption mode and on the period defined for the material master in the Customizing settings.

Note

ATP against planning is only executed for planned independent requirements that will be consumed by sales orders and not for dependent requirements.

Activities

To activate ATP against planning do the following:

  1. Make sure that the above mentioned prerequisites are fulfilled.
  2. When entering a sales order, enter the value KATP in the field Requirements type.

Note

This field is only available in the AFS sales order entry.

  1. Execute the availability check.

 

 

 

End of Content Area