 Displaying Relationships Between Operations

Use

In the DS planning board , you can hide and display charts with network views for operations. A network view for operations is a Gantt chart, in which the time position of operations and the relationships between the operations within an order are shown as blue lines, and the time position of operations and the relationships between operations from different orders are shown as yellow lines.

Prerequisites

You have defined a network view chart for operations, in the customizing for the DS Planning Board.

For more information, see the Implementation Guide for the DS Planning Board under Maintain planning board profiles .

Procedure

Displaying a network view chart

  1. Select the desired operations.

  2. Choose Start of the navigation path Extras Next navigation step Network view of operations End of the navigation path

  • Display as chart, if the network view should be shown as a chart within the DS planning board

  • Display as a dialog box , if the network view should be shown as an extra dialog box

Hiding a network view chart

Choose Start of the navigation path Extras Next navigation step Network view of operations Next navigation step Hide chart. End of the navigation path