Process APO Release in Product Planning Table and Product View The following functions are available in the
Product Planning Table
or in the
Product View
:
Display SA releases
Compare current release with previous release
Generate operative delivery schedules
Generate forecast/planning delivery schedule
Enter confirmations
Display alerts
In the
Product view: Periodic
or
Product view: Single Elements
chart you can view, enter or change the scheduled quantities.
You can branch to the function for displaying releases and confirmations.
Select the chosen item (LP-EIN). Choose
(
Process Procurement Scheduling Agreement Releases),
and then in the subsequent menu
Display Scheduling Agreement Releases
.
Select the chosen item (LP-EIN). Choose
(
Process Procurement Scheduling Agreement Releases),
and then in the subsequent menu
Compare Current/Previous Release)
.
Select the chosen delivery schedule. Choose
(
Process Procurement Scheduling Agreement Releases),
and then in the subsequent menu
Generate Operative Delivery Schedule
You can notify your vendor of up to nine last deliveries in an SA release.
Select the chosen delivery schedule. Choose
(
Process Procurement Scheduling Agreement Releases),
and then in the subsequent menu
Generate Forecast/Planning Delivery Schedule
.

When you generate scheduling agreement releases the system may issue messages. To see these messages, choose
Goto
→
Display Messages
You can branch to the function for entering confirmations.
Select the chosen delivery schedule. Choose
(
Process Procurement Scheduling Agreement Releases),
and then in the subsequent menu
Enter Confirmations
.
To access the
Alert Monitor for example, use the right mouse button or choose
Go to
→
Alert Monitor
.
For further information, see
Alert Monitor
in the SAP Library under
Supply Chain Monitoring
.
In the product view, on the
Periods
tab page, or in the product planning table, you can also create SA releases for selected delivery schedule lines:
Select the chosen item (SchLne) and choose
.
In the context menu, choose
Create Operative Delivery Schedule
or
Create Forecast/Plng Schedule
.
If you enter or change a requirement in the product planning table, choose ENTER. The system issues a message advising you that the order or schedule line was created successfully or (if applicable) with a delay.

Operative delivery schedules are displayed as new orders with the
category
SAg Rel
. Forecast/planning delivery schedules, that is long-term requirements (fixed) that are transmitted to the vendor and are not delivery-relevant, are not displayed.
The following categories exist:
Scheduling agreement schedule lines (SchLne)
These are quantities generated automatically in the planning run or created manually by the materials planner that have not yet been transmitted to the vendor.
Operative delivery schedule (SAg Rel)
These are short-term requirements (fixed) transmitted to the vendor that are delivery-relevant.
Confirmation (SA-ConfRel)
These are schedule lines/quantities confirmed by the vendor.
Shipping Notification/Inbound Delivery (BS-AVI),
When the inbound delivery is posted in the SAP R/3 system, the data is transferred to the SAP APO system via the CIF.

The new data completely replaces the last transmitted data in the liveCache. In the SAP APO system, only the operative delivery schedules are needed in the liveCache: forecast/planning schedules are not needed.
The liveCache contains the following categories: SchLne, SAg Rel., and PO memo (shipping notification).
The database contains additional data on operative delivery schedules, forecast/planning schedules, and acknowledgments.
For more information, see Creating Scheduling Agreement Releases