Displaying the Fill LevelIn the detailed scheduling planning board , you can display and hide charts with fill level curves that represent the fill level over time for container resources .
The minimum production quantity specified in the master data for the resource and the maximum stock level are displayed in the diagram section by a red line. By double-clicking on the fill level curve, you can display a complete list of all operations that fill or empty the container resource and you can navigate further from there.
You have defined a fill level chart in Customizing for the DS planning board.
For more information, see the Implementation Guide for the
DS Planning Board
under
Maintain planning board profiles
.
Displaying the fill level chart
Select the required resources.
Choose
Display as chart, if the fill level chart should be shown within the DS planning board
Display as a dialog box
, if the fill level chart should be shown as an extra dialog box
Hiding the fill level chart
Choose