 Selecting Objects to be Scheduled

Use

You can select activities, operations or orders that you wish to schedule as follows:

In choosing a specific object, you automatically choose further objects, as follows:

  • By choosing an order, you choose all operations in that order.

  • By choosing a resource, you choose all the operations on the resource whose start date/time falls within the planning period .

  • By choosing an activity on the detailed scheduling planning board, you choose the entire operation.

When you create an order in the SAP APO system or transfer an order to the SAP APO system, the chosen orders are the order and its component orders.

Note Note

So that the scheduling remains consistent in accordance with your detailed scheduling strategy the system not only schedules the chosen objects, but may also automatically schedule further objects:

End of the note.
  • If you schedule with an insert scheduling mode , the system must move operations to a resource in order to create slots for an operation to be inserted, or to close gaps.

  • If you have specified that time relationships or pegging relationships are to be adhered to, the system must also schedule or reschedule dependent objects accordingly.