Updating Matrices This procedure describes how to start the planning run for the Rapid Planning Matrix (RPM). You can update existing matrices for all
RPM products
or for individual RPM products and create new matrices.
You have used
Model Mix Planning
or the
Plan product
function in the
Product view
to generate planned orders for the RPM product that are assigned to the pegged sales order.
Choose
Production Planning
, then
The initial screen for the planning run appears.
Enter the
planning version
and specify whether the planning run is executed for all RPM products that have planning file entries by selecting
All Marked RPM Products
. If you only want to plan specific RPM products, choose
Select Products
and enter the product number and location.
To define whether or not the system should Generate RPM Time Series after the RPM run choose one of the following settings:
If you select
Generate Directly
, the system creates RPM time series, even if you have excluded this action in the control data of the product.
If you select
According to Settings
, the system behaves according to the setting in the control data.
If you select
Do Not Generate
, the system does not generate any RPM time series.
Check and, if required, change the control parameters for the planning run.
Parallel Processing
When you set the indicator, you define that the planning run is to be processed in parallel. See also: Parallel Processing During the Planning Matrix Run .
In the Background
You can define if the matrices are updated in the background.
To start the planning run, choose
.