Displaying, Maintaining, and Deleting Sales Scheduling Agreements You use this function to maintain selected data of a sales scheduling agreement in the SAP APO system. This means that in one function, you can assign or change control profiles and confirmation profiles, activate or deactivate sales scheduling agreement items, and manually enter scheduling agreement (SA) releases.
You can delete inactive sales scheduling agreement items in the SAP APO system.
You can also display SA releases and confirmations, as well as last deliveries.
You can display and edit sales scheduling agreements, for example, assign control profiles or enter scheduling agreement releases.
On the tab pages
Forecast Header/F/P Delivery Schedule
and
Operative Header/Operative Delivery Schedule
you can enter sales scheduling agreement releases.
On the tab page
Additional Data
you can view additional data regarding sales scheduling agreements such as sold-to party, customer material, partner description, or unloading point as well as the customer-specific fields (/SAPAPO/CMDS_USR01-/SAPAPO/CMDS_USR05). (This data can also be taken into account during inbound processing. See also
Inbound Processing of Scheduling Agreement Releases
)
You should cancel or delete sales scheduling agreement items in the SAP R/3 system before you delete them in the SAP APO system. The sales scheduling agreement item canceled in the R/3 system becomes inactive in the SAP APO system and can then be deleted.
Note
If you deactivate sales scheduling agreement items in the SAP APO system only , then the corresponding sales scheduling agreement item is not deleted, nor is a reason for cancellation available in the SAP R/3 system.
This means that with the next change transfer from the SAP R/3 system, the sales scheduling agreement item is reactivated because the sales scheduling agreement was not canceled in the SAP R/3 system.
In the SAP APO system, you can only delete inactive sales scheduling agreements.
Note
If no follow-on documents exist you can also delete sales scheduling agreement items directly in the SAP R/3 system. These items then become inactive in the SAP APO system.
To assign or change profiles choose
Here, you can display SA releases and confirmations, as well as last deliveries.
In master data maintenance, choose
Releases/Confirmations
, to display releases and confirmations.
In master data maintenance, choose
Deliveries
, to display the last deliveries of a sales scheduling agreement item.
(See also Outbound Delivery and Goods Issue )
In the SAP R/3 system , choose
Choose the
Reason for Cancellation
tab page and select the reason for cancellation for the relevant item.
Choose
.
This deactivates the sales scheduling agreement item in the SAP APO system .
This means that in the SAP APO system, (in master data maintenance on the
Scheduling Agreement
tab page),
the status of the item changes
from
Active Sales Scheduling Agreement
to
Inactive Sales Scheduling Agreement
.
When the item is deactivated, due delivery schedules and confirmations are deleted.
In the linked SAP R/3 system, all the existing schedule lines in the sales scheduling agreement are deleted and a schedule line with a quantity of zero is generated.
If you use confirmations, then a confirmation is sent to your customer with a quantity of zero on deactivation.
Note
You can use
to deactivate an active sales scheduling item in master data maintenance and activate an inactive item.
On the initial screen make the setting that you only want to delete inactive sales scheduling agreements.
You can also carry out the deletion first in the test run. In the log, you can see whether the sales scheduling agreement item can be deleted, whether it is active and in how many orders it is still being used.
Select the sales scheduling agreement item and choose
Delete.