Show TOC

 Consistency Check

The consistency check can be carried out at two different points in time:

  • When an integration model is being generated, the model to be generated is analyzed.

  • When integration models are being activated, the check is carried out on active integration models, including integration models that are to be activated, but not including integration models that are to be deactivated.

As a result of the check, a dialog box appears that displays a corresponding message.

Example Example

The consistency check applies if, for example, requirements are to be transferred but you did not consider the appropriate material master when you selected filter objects.

End of the example.

The following list indicates what each filter object is being checked for:

Filter Object

Contained in (active) integration model?

Material

Plant

Production process model (PPM)

Material master, resource

Resource

Plant

Plant

Is the time zone maintained?

Customer

Is the time zone maintained?

Vendor

Is the time zone maintained?

Stock

Material master

Special stock at customer

Customer

Special stocks with vendor

Vendor

Planned independent requirement

Material master

Purchase order

Material master

Planned order

Material master

Sales order

Material master

Material consumption data

Material master

Production campaign

Material master, production order

Manual reservations

Material master

Manufacturing order

Material master

ATP check for materials

Material master