Assigning Production Resources Automatically The function for automatic assignment enables you to maintain line balance relationships quickly between a production resource and the line elements in a line structure.
You cannot use this function if you wish to assign different production resources.
You have loaded the line balance in the navigation area and opened the complete line structure by choosing the
Expand
function button.
Alternatively, you have loaded the line structure in the navigation area and created a
filter
with the line balance.
Double-click a line element from the line structure in the navigation area.
The system displays the header data and the tab pages for the selected line element on the right-hand side of the screen.
Choose the
Prod.
Resources
tab page.
The system displays the tab page for maintaining data.
Select the
Automatic Assignment
function button.
The
Automatic Assignment of Production Resources
dialog box appears
.
Enter the required line network or line in the
Structure to be Exploded
field. In the
Types to be Assigned
field, enter
Line Segment
when you wish to assign production resources to activities on the level of line segments, or
Work Area
when you wish to assign them on the level of work areas.
Enter the name of the production resource you wish to assign in the
Name
field.
The system displays the number of production resources.
Choose the
Assign
function button.
You have automatically assigned the required production resource to all the line elements of the specified type.