Show TOC

 Displaying Pegging Relationships Between Orders

Use

In the DS planning board , you can hide and display charts with network views for orders. A network view for orders is a Gantt diagram in which the position of orders in relation to time and the pegging relationships between orders are displayed. Green lines are used to display dynamic pegging relationships; red lines are used to display fixed pegging relationships.

Prerequisites

You have defined a network view chart for orders, in the customizing for the DS Planning Board.

For more information, see the Implementation Guide for the DS Planning Board under Maintain planning board profiles .

Procedure

Displaying a network view chart

  1. Select the desired orders.

  2. Choose Start of the navigation path Extras Next navigation step Network view of orders End of the navigation path

  • Display as chart , if the network view should be shown as a chart within the DS planning board

  • Display as a dialog box , if the network view should be shown as an extra dialog box

Hiding a network view chart

Choose Start of the navigation path Extras Next navigation step Network view of operations Next navigation step Hide chart. End of the navigation path