Capacity and Resource Consumption for PP/DS Resource CategoriesThe following table shows the possible values for capacity and resource consumption for the resource types you use in PP/DS for planning in-house production. For the single-mixed and multi-mixed resources , for which you define a time-specific capacity and a period-specific capacity, and which are therefore used in both PP/DS and SNP, only the time-specific capacity relevant to PP/DS or the resource consumption relevant to PP/DS is described.
Possible values for capacity and resource consumption for PP/DS resource types
Resource Type |
Description |
Capacity |
Resource Consumption |
|
Fixed |
Variable |
|||
Single-activity resource Single mixed resource |
Can only process one activity at a time |
1 |
1 |
Not possible |
Multi-activity resource Multi-mixed resource |
Can process several activities simultaneously. Activities share the resource’s capacity |
Value in any unit of measurement To represent a machine group, enter a whole number without a unit of measurement for the number of machines. |
Value and unit of measurement of the required capacity |
Only possible for fixed activity duration |