Displaying the Results of Reorder-Point-Based Planning You can display the planning resultsof reorder-point-based planning, just like the planning results of period-based planning, in the DRP matrix . However, since reorder-point-based planning is static, i.e. not time-based, the system does not display the key figures of the DRP matrix for the individual DRP planning periods. The DRP matrix of a location product planned on a reorder-point basis consists of just one column, which contains the planning results.
You get to the
DRP Matrix
screen from the
SAP Easy Access
screen under
.
You can display and change the documentsgenerated by DRP on the basis of reorder-point-based planning on the
External Procurement – Delivery Schedule Maintenance
screen.
You get to this screen on the
SAP Easy Access
screen by choosing
.
If you plan a location product in reorder-point-based planning mode, the system displays the following additional key figures in the DRP matrix:
Note
You can only display and not process or change these key figures.
Reorder Point
This is the value you specified in the location product master data on the
SPP DRP
tab in field
Reorder Point.
Maximum Stock Level
The system only displays this key figure if you have set the
Round to maximum stock level
indicator on the
SPP DRP
tab in the location product master data. In this case the key figure contains the maximum stock level defined in the
Maximum Stock Level
field on the
SPP DRP
tab in the location product master data.
Additional Demand (BAdI)
The system displays this key figure only if you have implemented the Business Add-In (BAdI)
BAdI:
Determine Additional Quantities for Reorder-Point-Based Planning
(/SAPAPO/ROP_ADDITIONAL_QTYS).
Additional Receipt (BAdI)
The system displays this key figure only if you have implemented the BAdI
BAdI:
Determine Additional Quantities for Reorder-Point-Based Planning
(/SAPAPO/ROP_ADDITIONAL_QTYS).
The documents generated by DRP as the result of reorder-point-based planning, just like all other documents generated by DRP, can be viewed on the
External Procurement – Delivery Schedule Maintenance
screen. You can recognize a document as the result of reorder-point-based planning by the entry
with the quick info
Reorder Point Based
in the
MB
column.