This workflow template makes it possible to inform the person or persons at the work centers involved in the execution of an order, about the processing status of the operations.
When the operation of an order is released, the standard task
TS20000015
is started by the event
Operation released. This task starts work item X. When the order is partially or completely confirmed, the work item X is terminated, as it has partial or final completion as a terminating event.
When partial confirmation is performed for the operation, the standard task
TS20000056
is started by the event
Operation partially confirmed. This task starts work item Y. The operation is now processed further, and final confirmation is performed for it. Now work item Y is terminated, as it has the final confirmation as a terminating event.
Now the standard task
TS20000016
is started by the event
Operation completely confirmed. This task starts work item Z. To close work item Z it must be ended manually.