Use
You can use report RCATSPS (Time Sheet: Transfer to Project System) to transfer time sheet data to Project System. The report generates confirmations for networks and, if necessary, goods movements for backflushes.
You can transfer time sheet data that is assigned the
processing status 30 (Approved) or 60 (Canceled). The report transfers the data from the interface table CATSPS to Project System.To call the report, choose Time sheet ® Transfer ® Project system ® Transfer.
Integration
When the system generates confirmations for networks, it triggers activity allocation in Controlling at the same time.
Prerequisites
The control key must specify that the operation may be confirmed. If it does not, the data is transferred to Controlling.
Recommendation
Transferring canceled data to Project System can adversely affect system performance. When the report transfers canceled records, it reads all the confirmations for the relevant operation for each cell that has been changed in the time sheet. The burden on the system increases accordingly.
We recommend therefore that you
The more confirmations generated for a network, the poorer the report's performance when canceling confirmations.
Features
Selection
Output
If you select the Log option, the system displays a log after the transfer is complete.
If the report was not able to post some of the records in Project System, it also generates an error pool. The records containing errors are flagged as transferred. You can postprocess them in Project System. Note however if you do this that the data in Project System is no longer consistent with the data in the Time Sheet.