Entering content frameFunction documentationMaterial-Dependent Rate Locate the document in its SAP Library structure

Use

If you work with a line hierarchy without line balancing and only produce one material at a time, then you can produce materials with various rates. In takt-based scheduling, Sequencing overrides the planned rate for the materials for which you have entered material-dependent rates. Sequencing schedules all materials, for which you have not entered a material-dependent rate, with the general planned rate for the production line.

Note

If you work with a line hierarchy with line balancing, you can enter a model mix in the line balance. Therefore, material-dependent rates are not planned for this process.

Integration

Sequencing includes the material-dependent rates in takt-based scheduling.

Prerequisites

You have selected the indicator No line balancing for the line hierarchy. You can select this indicator on creating the line hierarchy or in the tab page Administration data.

Features

This graphic is explained in the accompanying text

See also:

Structure link Example 4 for Scheduling

 

 

 

 