Entering content frameProcess documentation Worklist for Notifications Locate the document in its SAP Library structure

Purpose

Using the worklist for notifications for a maintenance or service order, you can group together similar notifications for processing. To do this, you must enter a maintenance task list in the maintenance or service notification.

The functions are relevant for the following notifications:

 

The automatic creation of operations for the order occurs when you:

The system explodes the task lists assigned to a notification, copies the operations from the task lists into the order, and writes the notification to the object list of the order. The relationship between the notification and the operation can still be traced in the order.

Example

Using the worklist for notifications, you can, for example, group together all notifications for a particular building or for a particular work center, and optimize the maintenance activities for which a special analysis chest is required.

Each notification contains the tasks for later execution in the operations of the task list. The grouping of notifications for an order makes it significantly easier to, for example, print shop papers and make confirmations.

Prerequisites

The following prerequistes must be met:

You should, if necessary, assign a task list to the maintenance items of maintenance plans that create maintenance or service notifications.

Process Flow

  1. You create notifications in the SAP system in one of the following ways:

Maintenance plan scheduling causes the system to create a maintenance or service notification when the maintenance calls for every maintenance item of a maintenance plan fall due. The task list from the maintenance item is included as a reference in the notification.

  1. When creating a worklist for notifications, you must pay attention to the following:

If you call up list processing for notifications in change mode, you can display notifications and select the ones that you wish to group together in the worklist for the order.

For more information, see Create and Process Worklist for Notifications.

  1. When you create a worklist, the notifications are grouped as follows:

When you are assigning the notification, the system copies the operations from the task list specified in the notification to the order. The sequence of the operations represents the sequence of the notifications in the object list to which they are assigned.

If there is no task list specified in the notification, the system creates a dummy operation for this notification in the order.

  1. You can print out and process the order with all of its operations.
  2. You confirm the completed activities to the order.

 

 

Leaving content frame