Entering content frameFunction documentation Settling Planning Data for Orders and Projects Locate the document in its SAP Library structure

Use

You can settle planning data from internal orders and projects just like you settle actual data (see Settling Orders/Projects).

Prerequisites

Features

Two different functions are available for settling planning data from internal orders and projects - one for settling plan-integrated objects and one for transferring projects which are not plan-integrated. If results analysis has been carried out for the object you are settling, the system settles the results, otherwise all the plan costs and revenues are settled. The following table gives you an overview of which function to use when:

Object

Integrated planning

Function

Results analysis

Basis

Internal order

       
 

X

Settle

 

Cost plan

Project

       
 

X

Settle

 

Cost plan

   

Transfer

X

Planned results

 

X

Settle

X

Planned results

 

Integrated planning makes it possible for all plan allocations (cost element and activity input plan, assessment, and so on) to be updated automatically on the sender or receiver cost center or process. For more information on this, see Structure link Integrated Planning of Internal Orders.

Of the alternatives for projects listed above, settlement of plan-integrated projects without a results analysis key and transfer of projects that are not plan-integrated with a results analysis key are the standard uses. An example of a situation where you might use the former is a marketing event, where no revenues are generated and where the integration with Cost Center Accounting is required for calculating activity prices in the participating cost centers. The latter, on the other hand, could be used for construction of a power plant, where the costs were planned at the network level. Since networks are not plan-integrated, the entire project is not plan-integrated.

Activities

Setup

Before you can settle or transfer plan costs, you need to carry out the following steps:

Plan Settlement

The functions for settling order and project planning data are found in the CO-PA application menu under Planning ® Integrated planning ® Transfer order/project plan. These functions can only be used with plan-integrated internal orders and projects. In CO version maintenance for the settings by fiscal year, the "Integrated planning" flag must be selected for both the sender object and the CO version in which the settlement is carried out. For projects, the individual WBS element also must be plan-integrated.

When you settle planning data, the sender objects are credited.

Planning Data Transfer

The functions for transferring project planning data are found in the CO-PA application menu under Planning ® Integrated planning ® Transfer order/project plan. These functions are only supported for projects with a results analysis key that are not plan-integrated.

This function makes it possible to take your planned projects into account in your profit plan. When you transfer planned project data, the sender project is not credited.

 

 

 

 

 

Leaving content frame