Budget Objects Consistency Check
Use
This function enables you to carry out the consistency check for budget objects in a budget structure (BS), which you have defined using individual objects.
The system checks if a complete hierarchy of budget objects is guaranteed and if superior objects for all budget objects exist.
Features
Consistency in the BS is guaranteed if:

BS consistency is met if the superior budget object is not more than "1 center level and 0 item levels" or "0 center levels and 1 item level" away.
Activities
In the event of an error, the following happens:
In the dialog box Document lines: Display messages the system displays a list of all budget objects for which no superior budget objects are defined.