Entering content frameProcedure documentation Changing a BOM Header Locate the document in its SAP Library structure

You can goto the BOM header from various screens:

  1. Click This graphic is explained in the accompanying text.

You can process header data on several tab pages:

See also:

Maintaining header data

  1. After the changes save the BOM.

Change to a BOM Header: Example

The BOM for the Racing bicycle MRB01 (Plant 0001, Usage 01) is changed with change number CH01 . The valid-from date for the change (07/01/1996) comes from the change number.

The alternative text of BOM MRB01 is changed. When you make a change with reference to a change number, the "old" value of the field is retained. The system creates a new BOM header for the BOM.

Before the change

Validity Period

Valid from:

14.05.1998

Valid to:

01.07.1998

Alternative text

Blue model

After the change (change number CH01 )

Validity Period

Valid from:

01.07.1998

Valid to:

31.12.9999

Alternative text

Color model: blue frame

 

Note

If you display the changed BOM over its entire validity period, you see two different header records in the Header overview for BOM MRB01 (Plant 0001, Usage 01).

 

 

Leaving content frame