Entering content frameProcedure documentation Changing Items on the Item Overview Locate the document in its SAP Library structure

You cannot change the following data on the item overviews for materials, documents, and classes:

You enter this description in the master record (for example, material master record, document info record, or class).

The system sets this indicator automatically.

The system sets this indicator automatically.

You can only make certain changes to the following data:

You cannot enter certain data, such as a component number.

You cannot change the component quantity on the item overview.
The system calculates the item quantity from the sum of the sub-item quantities (sub-item overview).

The component unit of measure is always PC (piece).

You can change all the other fields that are available for entry on the item overview screen. You can, for example, replace a component or change a quantity.

Change to an Item: Example

The BOM for the R acing bicycle MRB01 is changed with change number CH01 . The valid-from date for the change (07/01/1996) comes from the change number.

Item 0010 BRLV (Brake lever), created on 05/14/1996, is changed as follows:

If you display the changed BOM over its entire validity period, you see two different item records for item 0010 BRLV (Brake lever) in the item overview.

Before the change

Validity period

Valid from:

05/14/1998

Valid to:

07/01/1998

Component quantity

1 piece

No sub-items exist

 

After the change (change number CH01 )

Validity period

Valid from:

07/01/1998

Valid to:

12/31/9999

Component quantity

2 pieces

Sub-items exist

Leaving content frame