If you make changes to a material with reference to a change number, you can assign a revision level to specific change statuses. This allows you to process the objects later with reference to either a change number or a revision level.
In Customizing for Logistics General, you can activate revision levels for your company by choosing Engineering Change Management
Before you can assign a revision level to a material for a specific change number, the following requirements must be met in the change master record:
You can either enter this manually or have it generated automatically by the system. To have it generated automatically, you must set the indicator Object management record generated in the change master record.
The indicator for the processing status of a material is unique. This means that you can only assign one revision level to the material (BOM header material) for a change made with reference to a specific change number (for example, CH01).
You can only assign a new revision level for a change made with reference to a different change number.
You can assign a revision level to a material either from engineering change management or directly when processing the material (for example, in the material master record or in the BOM). This section describes how to process a revision level from BOM processing functions.
The table below shows BOM changes for material AA, plant 0001, usage 01. The changes are made with reference to three change numbers. Two changes also have revision levels assigned to them.
Changes to the BOM for material AA
Change number |
Valid-from date |
Revision level assigned |
AA |
01/01/1998 |
yes (01) |
BB |
02/01/1998 |
|
CC |
03/01/1998 |
yes (02) |
This means that material AA has the following revision levels: 01 and 02.
You can process the material on 01/01/1998 using change number AA or revision level 01.