Entering content frameConceptual documentation Before You Create Your BOM Locate the document in its SAP Library structure

Before you create a multiple BOM, please note:

If so, which change number do you use?

If you want to make the change with reference to an engineering change request (ECR), the ECR must first be converted to an engineering change order (ECO).

Multiple BOM: Example

One model of the racing bicycle HRR01 is produced in blue. The assembly BLUE_FRAME contains component PAINT01 (blue paint).

This component is also an assembly, and contains the following material components:

Depending on the lot size, the quantities of these components change. There are 3 alternative BOMs (alternatives) for assembly PAINT01:

Alternative 1 Lot size 1-100

Alternative 2 Lot size 101-200

Alternative 3 Lot size 201-1,000

The following graphic shows the 3 alternatives of multiple BOM PAINT01.

 

This graphic is explained in the accompanying text

 

 

 

 