Entering content frameConceptual documentation Before You Create Your BOM Locate the document in its SAP Library structure

Before you create a variant BOM, please note the following:

If so, which change number do you use? If you want to make the change with reference to an engineering change request (ECR), the ECR must first be converted to an engineering change order (ECO).

Variant BOM: Example

The racing bicycle HRR01 is produced in the following color options:

This means that there are 3 similar products (variants) with different colored frames.

There are 3 different variants of assembly Preassembled frame and forks:

FRAME01 With component FR01 (Blue frame)

FRAME02 With component FR02 (Red frame)

FRAME03 With component FR03 (Black frame)

The following graphic shows the 3 variants in the variant BOM for this bicycle.

 

This graphic is explained in the accompanying text

 

 

 

 

Leaving content frame