In your BOM, component scrap is maintained for a material component. The component quantity must be adjusted to include the scrap.

Material component HBAR – component quantity:

1,000 pieces

Component scrap:

5 %

® Scrap quantity:

50 pieces

1,050 pieces of component HBAR (handlebar assembly) are required.

Component Scrap and Assembly Scrap

Assembly scrap is maintained in the material master record of assembly BIKE. In your BOM, component scrap is maintained for a material component. The component quantity must be adjusted to include the scrap.

Quantity of BIKE to be produced (required quantity):

1,000 pieces

Assembly scrap (HBAR):

10 % (100 pieces)

® Adjusted required quantity:

1,000 pieces

Plus component scrap for HBAR:

5 % (55 pieces)

® Total scrap quantity for HBAR:

155 pieces

If an adjusted required quantity of 1,100 pieces of racing bicycles is to be produced, 1,155 pieces of component HBAR (handlebar assembly) are required.

 