Entering content frameObject documentation Replenishment Lead Time Locate the document in its SAP Library structure

Definition

Total time for the in-house production or for the external procurement of a product. In in-house production, the replenishment lead time is determined to cover all BOM levels.

Use

As a rule, the replenishment lead time is used in the availability check. If the replenishment lead time is not maintained, then the system uses the in-house production time or the planned delivery time to determine component availability. If both are maintained, the in-house production time or the planned delivery time have higher priority than the replenishment lead time.

Integration

This graphic is explained in the accompanying text

The replenishment lead time is interpreted as follows:

 

 

 