Entering content frameFunction documentation Displaying/Changing/Deactivating Detailed Planning Locate the document in its SAP Library structure

Use

You can use detailed planning to enter detailed planning data for a given cost element.

For more information on detailed planning, see the SAP Library under Financials ® CO Controlling ® Cost Center Accounting ® Cost Center Planning ® Manual Planning ® Detailed Planning of Cost Elements, Executing Detailed Planning.

Activities

To enter detailed planning data on a cost element, proceed as follows:

  1. Select a planning row.
  2. Choose Edit ® Display/Change detailed planning.
  3. To cancel detailed planning data, choose Edit ® Deactivate detailed planning.

 

 

Leaving content frame