Use
Report with which you can analyze planned costs using product drilldown in Product Cost by Order. The reporting time frame can be cumulative or limited.
This report displays the planned costs and plan quantities updated to an object and can be used in the analysis of planning data.
In Product Cost by Order, the planned costs on a costing object result from the preliminary cost estimate of the manufacturing order.
Data Displayed
The following data is shown based on key figures and/or original cost elements:
Header Information
Prerequisites
You must create a preliminary cost estimate for the manufacturing order.
Notes
Product Cost by Period
No
planned costs are updated to the product cost collector during a preliminary costing of the product cost collector in Product Cost by Period (see also: Product Cost by Period Information System).See also:
See the following sections for information on preliminary costing in Product Cost by Order:
Preliminary Cost Estimate for Manufacturing Order Preliminary Costing of CO Production OrdersSee the following section for information on the presentation of values determined during preliminary costing of product cost collectors.
Preliminary Cost Estimates for Product Cost Collectors