Definition
Existing material cost estimates
Use
This report generates a list of existing material cost estimates according to various selection criteria.
You can select according to the following search criteria:
You can also suppress the display of input materials. To do so, set the indicator to No Material Components.
Structure
The standard report shows a header line for each material, and an item below that for each cost estimate that was selected for the material. The report offers you a range of preselected data. You can modify this structure to suit your own requirements by creating your own
layouts.Integration
You can access detailed reports for a cost estimate (for example, a cost component split or itemization) while in the list:
See also:
If you are using mixed costing, refer to
Special Processing with Mixed Costing.You can find information about the different functions for interactively processing results lists in the documentation for the
ABAP List Viewer.