Entering content frameProcedure documentation Displaying the Scheduling Overview as a List Locate the document in its SAP Library structure

Use

Using this report, you can create a work place-related list of all test dates for the selected testing schedule items in stability studies. When the system makes the selection, it only takes active testing schedules into consideration. If necessary, you can narrow the scope of the schedule overview using such selection criteria as testing schedule items, test dates, inspection plan data, and so on.

Note

If you select the Select work centers option, you can further restrict the selection on the basis of work centers. In this case, the system displays one line for each date, testing schedule item (storage condition), and work center. If you do not use the Select work centers option, you cannot limit the selection by work centers. If you specified work centers as a selection criterion, they will not be taken into consideration in this case. The system will display one line for each date and testing schedule item.

Procedure

  1. From the SAP Easy Access menu, choose Logistics ® Quality Management ® Stability Study ® Stability Planning ® Testing Schedule ® Scheduling Overview List.

The initial screen for the scheduling overview for stability studies appears.

  1. Enter your selection criteria and then choose Execute.

A list of results conforming to your selection criteria is displayed.

Leaving content frame