Maintenance of Evaluation Paths 
Here you will find the maintenance view Change evaluation paths: Overview.
To establish the permitted relationships for an object type, use report
When using an evaluation path in a view, you should consider the following:
When using an evaluation path in a rule for agent determination, you should consider the following:
Before creating new evaluation paths, check the evaluation paths available as standard.
Example
Starting from an organizational unit, evaluation path O-S-P establishes all persons who belong to this organizational unit or subordinate organizational units via their positions. Evaluation path O-S-P is defined as follows:
No. |
Object type |
A/B |
Link |
Link description |
Priority |
Type |
Skip |
10 |
O |
B |
003 |
includes |
* |
S |
|
20 |
S |
A |
008 |
holder |
* |
P |
|
30 |
O |
B |
002 |
is line manager of |
* |
O |
The relationship defined in the last line ensures that user assignments in subordinate organizational units are included in the evaluation path as well.
Since the indicator
Skip is not set in any of the lines, evaluations always display all the objects determined.Starting from a person or a user, evaluation path
WF_ORGUN first establishes the relevant position and then the organizational unit to which this position belongs. Evaluation path WF_ORGUN is defined as follows:No. |
Object type |
A/B |
Link |
Link description |
Priority |
Type |
Skip |
10 |
US |
A |
208 |
is identical to |
* |
P |
x |
20 |
* |
B |
008 |
holder |
* |
S |
x |
30 |
S |
A |
003 |
belongs to |
* |
O |
This evaluation path works both when the positions are occupied by users and when the positions are occupied by persons who are then assigned to users.
This evaluation path can be used with a user or a person as the starting point.
Since the
Skip indicator is set in the first two lines, evaluations only display the organizational units found recently.