Manually Create Planned Rate
Prerequisites
You have selected the indicator No line balancing either on creating the line balance, or in the tab page Management data.
Procedure
In the line hierarchy menu, select the tab page Planned Rates.The system displays the overview, in table form, of the planned production rates.
Enter the following parameters for each period, for which you want to enter the planned rate:
- The start and end date of the period of time for which the planned rate is to be valid. Make sure that the periods of time do not overlap. If overlapping occurs, the system takes on the last period of time entered and adjusts the previous period of time accordingly.
- The planned rate in the unit of measure displayed and if necessary the number of time units displayed.
Result
You have defined the planned rate of the production line for the periods entered. You can override the planned rate of a period in the short term, by
Creating an Operative Rate (e.g. for a shift).