Entering content frameProcedure documentation Creating Worklists Locate the document in its SAP Library structure

Use

You want the system to create a worklist of particular materials in the material list.

Prerequisites

You have entered the required selection criteria in the collective access to the MRP list or stock/requirements list and have called up the material list of all the materials that correspond to these criteria.

The material list includes the following for each material: traffic light, ranges of coverage, the number of exception messages per exception group, the current plant stock, and various other material data.

Procedure

  1. In the material list, select the materials for which you want to display the MRP lists or stock/requirements lists:

Note

You can find the required materials in two ways:

  1. To access the appropriate list, double-click the first material or choose This graphic is explained in the accompanying text Selected stock/requirements lists or This graphic is explained in the accompanying text Selected MRP lists.

The system displays the list for the first material.

  1. Choose Show material tree.

Result

The system displays all the materials that you selected in the material list in a worklist tree on the left-hand side of the screen. Double-click the appropriate material in this tree, or choose This graphic is explained in the accompanying text and This graphic is explained in the accompanying text, to change from list to list.