Entering content frameFunction documentation PDC Data Transfer via Communication Channel 2 (CC2) Locate the document in its SAP Library structure

Use

It is possible to enter completion confirmations for a production order in a subsystem and to import them into R/3 via a PDC data transfer. This means that you can enter a confirmation close to production in a non-SAP system and process it in R/3.

Prerequisites

To execute the PDC data transfer, the following requirements must be met:

The communication parameters are maintained in Customizing by choosing Cross Application Components ® Plant Data Collection ® Production Orders (PP, Communication Channel 2) ® Define communication parameters.

Features

With the download function you can send data to a subsystem, so that input checks can be made in this subsystem. This function is not absolutely necessary for using PDC data transfer.

With the upload function you transfer the confirmations from the subsystem to the R/3 system. You can set up the system so that either the confirmations are updated automatically after they have been transferred (communication parameters) or a program is scheduled to do the update as a background job.

In general, the communication parameters are set up so that the update of the confirmations is triggered automatically.

In error processing, you can reprocess confirmations for which errors occurred during updating.

Note

You will generally schedule the relevant programs as background jobs. However, you can call up the PDC data transfer functions manually.

See also:

Structure link PP - PDC Interface

 

Leaving content frame