Entering content frameFunction documentation Progress confirmation Locate the document in its SAP Library structure

Use

The milestone confirmation is a form of confirmation, in which the confirmation of one operation causes preceding operations or sub-operations to be automatically confirmed at the same time. When you carry out a progress confirmation, you report the progress of the order by confirming the operation that you have reached (for example at the end of the day).

As opposed to milestone operations, you do not have to make any settings in the control key for operations that are to be confirmed with progress confirmation. You can select each confirmable operation.

If the operation has the relevant indicator in the control key, one speaks of Milestones rather than progress confirmation.

Caution

As opposed to other types of confirmation, progress confirmation requires you to enter the total quantity that has been produced, rather than the quantity that has been produced since the last confirmation. This means that the quantity that you enter in a progress confirmation is different from that of other types of confirmation, if you carry out confirmations for partial quantities.

Example

You produce 10 pieces of a material in total. You want to enter the confirmations in two steps, each time after 5 pieces have been produced.

Integration

You can combine progress confirmation with the other forms of confirmation. You should note the following:

Example

Operation 30 is marked in its control key as a milestone operation. You partially confirm operation 30 with a quantity of 50 pieces. Operations 10 and 20 are likewise partially confirmed with a quantity of 50 pieces. Then you enter a progress confirmation for operation 50 with a quantity of 100 pieces, which means that operation 50 is finally confirmed. Operation 40 is also finally confirmed with 100 pieces, whereas the confirmation data for operations 10 to 30 is not changed. To finally confirm these operations, you must make a confirmation for operation 30 with a total quantity of 100 pieces.

Example

Operation 30 is marked in its control key as a milestone operation. You want to enter a progress confirmation for operation 40 for a quantity of 50 pieces. The system does not allow you to create a progress confirmation for operation 40 until you confirm operation 30.

Example

You partially confirm operation 10 manually with a quantity of 50 pieces. You then confirm operation 30 with a progress confirmation with a quantity of 100 pieces. (This is a final confirmation). Operation 10 is still partially confirmed with a quantity of 50 pieces; operations 20 and 30 however are finally confirmed with quantities of 100 pieces.

Features

A progress confirmation is entered at operation level. When you enter a progress confirmation, all preceding operations are confirmed. The quantities for the automatically confirmed operations are determined automatically.

Example

You enter a progress confirmation for operation 30 for a quantity of 100 pieces. The preceding operations 10 and 20 are are automatically confirmed also with quantities of 100 pieces.

If progress confirmations already exist for a preceding operation, the quantity to confirm is determined by expanding to the total confirmed quantity of the operation.

Example

You have confirmed operation 30 with 40 pieces using a progress confirmation. You enter a progress confirmation of 90 pieces for operation 40. The system automatically produces a confirmation for operation 30 for the additional quantity of 50 pieces (=90 pieces - 40 pieces).

Note the following points regarding progress confirmation:

Example

You want to enter a progress confirmation for operations 30 and 50. You first enter a partial confirmation of 50 pieces for operation 50. All operations preceding operation 50 are automatically partially confirmed. You then enter a partial confirmation of 50 pieces for operation 30. Operation 30 remains confirmed with a quantity of 50, since the same progress level had already been recorded through in the first confirmation.

Example

Operations 10 and 20 each have a sub-operation. You confirm operation 20 with 50 pieces using a progress confirmation. The system automatically confirms operation 10 with the same quantity and its suboperation with its corresponding activities. You must confirm the sub-operations for operation 20 manually.

Example

You enter a progress confirmation for operation 20. Operation 20 receives the statuses MCNF and MILE. Operation 10 receives the status MILE.

Note

In collective orders, you can use progress confirmations to simultaneously confirm operations of more than one order (see Collective Orders: Example of Confirmations).

 

Leaving content frame