Use
You can release individual operations within a production order. Use this function if you want to process a production order without releasing the whole order.
Features
The following applies when releasing operations:
An operation can only be released if the preceding operation has been released.
Using Trigger Points to Release Operations
You can assign a trigger point to an operation in the routing or in the production order. You can release one, or several successive operations, using trigger points (see
Trigger Points). How to Create a Trigger Point explains how to assign a trigger point.Actions for Partially Confirmed Orders
The following actions can be executed for partially confirmed orders: