Use
If data is changed in the routing, in the work centers affected or in the BOM after order creation then these changes are not automatically taken into account in the production order.
Thus you can read in the master data (BOMs and routing) again into a created
or released production order.Features
If you decide to read in the master data again then it has the following consequences:
The status of a released order is set to created again.
The deleted data is then replaced by new data from the selection BOM/routing. The selection procedure is identical to the procedure for creating a production order (see
Selecting Bills of Material or Routing SelectionWhich Data is Read?
Only the master data that you select in the dialog box for reading master data is read in again.
You have specified that master data is to be selected using a new production version. The production version contains a valid routing and a valid BOM alternative. In the Read PP master data dialog box, however, you have only selected the field New routing. In this case the system does not select a new BOM.
The explosion date for the master data to be read in can be changed.
Read with Production Version
You can read in master data for a specific production version. In this case
the system selects the routing or BOM alternative that is determined by the production version.The following conditions must be fulfilled:
Read with Revision Status
You can read in master data for a specific revision status. In this case the system selects the
routing or BOM alternative with the date from the revision status.The following conditions must be fulfilled: