Entering content frameProcedure documentation Calling Up Cost Element Reports Locate the document in its SAP Library structure

Note

You can summarize cost elements into cost element groups. If you want the system to classify the commitment values for a single account assignment object, or for a group of account assignment objects, using each cost element, then enter a cost element group when calling up the cost element report.

Calling up Cost Element Reports for Order Commitments

Choose Accounting ® Controlling ® Internal orders ® Information system ® Reports for internal orders ® Plan / Actual comparisons ® Additional key figures ® Order: Actual/Plan/Commitments.

Calling up Cost Element Reports for Cost Center Commitments

Choose Accounting ® Controlling ® Cost Center Accounting ® Information system ® Reports for Cost Center Accounting ® Plan / Actual comparisons ® Additional key figures ® Cost centers: Actual / Plan / Commitments.

Calling up Cost Element Reports for Project Commitments

Choose Accounting ® Project system ® Information system ® Controlling ® Costs ® Plan-based ® Hierarchical ® Plan/Actual/Commitments/Rem. Plan/Assigned.

Results

To call up each line item report, double-click on the report row in the cost element report.

 

 

 