Use

If a resource refers to a specimen or material, and its price is changed, you must revaluate resource planning manually.

Procedure

To revaluate resources:

  1. In the planning menu for your application, choose Cost/activity input ® Change ® Extras ® Resource planning ® Revaluate.
  2. Specify which data is to be revaluated.
  3. To do this, maintain the following fields:
    1. Controlling area
    2. Version
    3. From period
    4. To period
    5. Fiscal year
    6. From resource
    7. To resource
  4. Choose Execute.

Result

The SAP R/3 System posts the resource consumption using the updated price. You can check the results on the overview screen and on the period screen for planning.