The confirmation data that is transferred to the R/3 system from the subsystem has to fulfill certain conditions from the application point of view. The confirmation must
- Take into account the current status of the operation (for example, you cannot confirm an operation that has not been released).
- Pay attention to the conversion of order unit of measure to operation unit of measure.
- Take into account how to react to overdelivery and underdelivery.
- Handle operation splits correctly.
- Take into account the sequence of time events in an operation.
- Take into account the sequence of confirmations referring to time tickets.
For a more detailled description of the application logic, refer to the PDC Interface component in