Entering content frameFunction documentation Dispatching and Deallocating Without the Planning Board Locate the document in its SAP Library structure

Use

You can use this function to:

Dispatching

Proceed as follows when dispatching:

  1. Dispatch an operation. The operation receives the status DSPT (dispatched). The capacity requirements are planned without capacity leveling.
  2. Note

    The system issues a warning if a capacity is overloaded.

  3. If necessary, change the operation dates of the dispatched operation (operation tab, Dates tab page).
  4. Midpoint scheduling is used when the order is rescheduled. The dates of the dispatched operation are not adjusted.

Activities

See also:

Structure link Executing Capacity Leveling (SFC)

Structure link Capacity Leveling in Shop Floor Control

 

 

Leaving content frame