Use
If you cancel a request for kanban replenishment in production, there are several possible situations that may require corresponding actions in PP and/or WM.
The following table provides an overview of the procedure you should follow when a kanban request is cancelled in PP.
Procedure
If you cancel the kanban request in PP and… |
Action |
The transfer requirement (TR) is still open… |
The system sets the status to ‘completed’. The kanban indicator is removed, canceling the transfer requirement. |
A transfer order (TO) has been generated for the TR but has not been confirmed… |
In each TO item, the system notes that replenishment was cancelled. When the TO item is confirmed, the system informs you of the cancellation process in the kanban. |
|
|
|
|
|
|
|
|
If you cancel a transfer requirement for which no transfer order has been created, the system deletes the reference to the kanban and the kanban indicator in the transfer requirement.
In the kanban, the system resets the transfer requirement number and the status of the kanban container. Even if you delete a transfer requirement, the system resets the reference to the requested replenishment in the kanban.