Entering content frameProcess documentation Inspection for a Goods Receipt Locate the document in its SAP Library structure

Purpose

The system can automatically create an inspection lot when a goods receipt is posted in the system. A goods receipt can be posted internally (for example, from production to the warehouse) or from an external source (for example, from a vendor). When the goods are received, they can be posted to one of several destinations:

If a goods receipt is posted to:

Note

If you post the goods to inspection stock, you can only post the goods out of inspection stock via the usage decision in QM.

Prerequisites

The system creates an inspection lot automatically for a goods receipt if the following conditions have been met:

Process Flow

  1. The system creates an inspection lot automatically when the goods receipt is posted in Materials Management (MM).
  1. If the inspector will record results for inspection characteristics (controlled by the inspection settings in the material master), the system assigns an inspection specification (for example, a task list or material specification) to the inspection lot. If the system cannot find a specification or if more than one inspection specification is assigned to the material, you must assign a specification to the inspection lot manually.
  2. If dynamic modification criteria are defined for the inspection lot origin or task list usage, the system checks the existing quality level for the material (and the other criteria, if applicable):
  1. The system calculates the sample size.

If the sample calculation must be triggered manually (controlled by the inspection settings in the material master), you must call up the inspection lot in the change mode and choose the function to trigger the sample calculation manually.

  1. If you are going to inspect the goods in the inspection lot using an inspection specification:

Result

You can use the information in the inspection instruction and sample-drawing instruction as a guide to:

When you have finished recording inspection results and/or defects, you can complete the inspection.

See also:

Structure link Results Recording

Structure link Defects Recording

Structure link Inspection Lot Completion

Leaving content frame