Procedure
The following table shows you the screens the system branches to depending on whether bills of material exist for the material.
Screen Sequence for Material Component Overview
If there is |
you reach the |
no bill of material for the material |
Material component assignment dialog box. You can branch directly to the bill of material maintenance and create a bill of material. |
one bill of material for the material |
Material Component Overview screen. |
several bills of material forthe material |
Choose Alternative BOM dialog box. Select the bill of material whose components you want to assign. |
The New Assignment screen appears.
– directly
– via an operation list
To display the operations to which you can assign material components, choose Operation list in the New Assignment dialog box. From here you can select an operation.
Result
The system assigns the material components to the operation.