Entering content frameProcedure documentation Simulating BOM/Task List Explosion Locate the document in its SAP Library structure

Use

In the configuration simulation, you can check the explosion of BOMs and task lists (such as routings). On the initial screen, you can define whether the BOM or task list is exploded.

If you select BOM, the entire BOM structure is exploded according to the settings in the configuration profile. You can display the individual assemblies on the result screen.

If you select Task list, only the task list of the header material is exploded, not the task lists of the assemblies.

Procedure

  1. On the initial screen of the configuration simulation, select BOM to display the entire structure on the result screen.
  2. If you have created more than one configuration profile for a material, you see a dialog box. Select a profile and choose This graphic is explained in the accompanying text Continue. If you want to call detailed information on the profile, choose This graphic is explained in the accompanying text Profile Detail or double-click on the profile.

  3. To display the task list of an assembly on the result screen, select the assembly and choose View ® Objects ® Task list.

You see the operations or activities in the task list that were selected for the assembly during configuration.

Note

Operations that have been changed by dependencies have an information icon next to them. You can display changes by choosing Information.

  1. To return to the BOM explosion, choose View ® Objects ® BOM.

 