Example for Variance Calculation Locate the document in its SAP Library structure

In this example, the target costs are compared with the control costs (net actual costs) for a production order. This example shows only variances on the input side.

The actual costs arise from goods movements in the Materials Management component, and confirmations in the Production Planning component or activity allocations in the Controlling component.

If...

then the system calculates...

the price of the material issued changes

an input price variance

the input quantity of a material changes

an input quantity variance

a material is replaced by a different
material

a resource-usage variance

the confirmed values are different from the standard values

an input quantity variance

the operation is performed at a different
cost center

a resource-usage variance

you have confirmed scrap (in Product Cost by Period at operation level, in Product Cost by Order at operation level or at order header level) and you have selected the indicator Scrap in the variance key and the indicator Scrap variances in the variance variant

scrap variances and reports them

The following tables provide an overview of the results of variance calculation. The first table shows the planned costs and actual costs for the order by cost element. The second table shows the same information by costing item. The third table shows the values that are calculated when variances are calculated for the order.

Order: Analysis by Cost Element

Resource

Cost Elements

Planned Costs

Actual Costs

Raw materials

400000

USD 20

USD 33

 

410000

USD 20

USD 20

Internal activities

610000

USD 75

USD 85

 

620000

USD 50

USD 50

Total costs

 

USD 165

USD 188

Order: Itemization

Plan Values for Resource

Quantity

Price

M WK01 ROH-1

2 units

USD 10

M WK01 ROH-2

2 units

USD 10

E KST1 LST1

15 min

USD 5

E KST2 LST2

10 min

USD 5

Actual Values for Resource

Quantity

Price

M WK01 ROH-1

3 units

USD 11

M WK01 ROH-3

2 units

USD 10

E KST1 LST1

17 min

USD 5

E KST2 LST3

10 min

USD 5

Results of Variance Calculation

Cost Element

Variance Category

Value

400000

Input price variance

USD 3

400000

Input quantity variance

USD 10

410000

Resource-usage variance

USD 20 (+)

410000

Resource-usage variance

USD 20 (-)

610000

Input quantity variance

USD 10

620000

Resource-usage variance

USD 50 (+)

620000

Resource-usage variance

USD 50 (-)

 

Total variance

USD 23

 